Activity-on-Node Diagrams.

Chapter 8 notes can be download link below.

Download link
http://we.tl/0UmlQIfEMw

Chapter 8 Homework Assignment

Chapter 8

Questions

1.    Draw an Activity-on-Node Diagram for the following:
Activity Name    Predecessor(s)
A    None
B    None
C    A
D    A,B
E    B
F    C,D,E

2.    Draw an Activity-on-Node Diagram for the following:
Activity Name    Predecessor(s)
A    None
B    None
C    A
D    A,B
E    D
F    E
G    C
H    F,G

3.    Should the critical path activities be monitored differently from non-critical path activities for a project by a project manager?  Explain your response.

4.    Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:
Activity Name    Predecessor(s)    Duration (Weeks)
A    None    5
B    None    10
C    A    10
D    A,B    30
E    D    10
F    E    15

5.    Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity,  and project critical path for the following:
Activity Name    Predecessor(s)    Duration (Weeks)
A    None    5
B    None    10
C    None    10
D    A,B    5
E    C    15
F    C,D    10
G    E,F    5

6.    Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity,  project duration, and project critical path for the following:
Activity Name    Predecessor(s)    a    m    b
A    None    5    30    40
B    None    10    20    50
C    None    5    15    30
D    A    5    10    30
E    B,C    15    20    25
F    C,D    15    20    60
G    F    10    20    50

Solution