The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start Wednesday July 3rd, 2011, and be completed in time for the start of the 2014 season. A Penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.
Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes.
Questions: 1. Draw the network including ES, LS, EF, LF and the slack for each activity. Also indicate the critical path plus complete the Gantt chart3. 2. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a none-page Gantt chart for the stadium schedule.