Need to develop aggregate schedule for widget maker. Costs and 4 quarter forecast are provided below. Quarter Forecast

Comparative Corporate Governance Academic Essay
August 19, 2020
Health Care Academic Essay
August 19, 2020

Need to develop aggregate schedule for widget maker. Costs and 4 quarter forecast are provided below. Quarter Forecast

Need to develop aggregate schedule for widget maker. Costs and 4 quarter forecast are provided below.

Quarter Forecast
1 1400
2 1200
3 1500
4 1300

Costs

Prior quarter output 1500 units
starting inven 0 units
stockout cost for back
orders $50/unit
inven holding cost $10/unit for every unit held at end of quarter
hiring workers $40/unit
layoff workers $80/unit
unit cost $30/unit
overtime $15 extra per unit
subcontracting $ na

Questions

a. Try a chase plan by hiring and layoffs to meet forecast as necessary.
b. use a plan that holds employment steady
c. which is the more economical plan.