Management Construct MS Project plan
Problem 1
Construct MS Project plan for the project below. Project starting date is September 14, 2014 (using standard calendar)
Activities Duration Predecessors Resource Normal Time Min Time Cost – Normal Time Cost – Min Time Crash Cost per Day
A 10 days X (100%) 10 9 $500 $800 $300
B 11 days A X (100%) 11 9 $1,000 $1,800 $400
C 10 days A Y (100%) 10 9 $2,000 $2,700 $700
D 11 days A X (100%), Y (100%) 11 9 $1,000 $1,900 $450
E 6 days B,C,D Z (100%) 6 5 $1,600 $2,200 $600
F 9 days E X (100%), Y (100%) 9 7 $1,500 $3,300 $900
G 8 days E X (100%) 8 6 $600 $1,800 $600
H 10 days F,G Z (100%) 10 9 $1,600 $2,400 $800
1. What is the project duration
2. What is the project finish date
3. List the Critical Path(s)
4. Fill the following table.
Activity ES EF LS LF F. Slack T. Slack
C
E
G
5. Key in resource usage information. Does Resource X over allocated? If so, from what date to what date?
6. List the crashing cost for this project (choose the activity to crash based on lowest crashing cost).
Total Crashing Date 1 Day 2 Days 3 Days 4 Days
Cost
7. If the company has $1,400 extra resources put into this project, what is the new project duration?
Construct a NEW MS Project plan for the project below. Project starting date is October 31, 2014 (using standard calendar)
Activities Duration Predecessors Resource % Complete Actual Cost
1. Preparation Phase
1.1 A 11 days X (80 Hours) 100% $920
1.2 B 6 days A X (40 Hours) 100% $450
1.3 C 5 days A Y (40 Hours) 100% $600
2. Installation Phase
2.1 D 12 days B,C X (50 Hours), Y (60 Hours) 100% $1,500
2.2 E 9 days D Z (70 Hours) 100% $1,600
2.3 F 8 days E X (60 Hours), Y (70 Hours)
3. Testing Phase
3.1 G 8 days E X (40 Hours)
3.2 H 10 days F,G Z (100 Hours)
Resource Name Max Rate Overtime Rate
X 100% $10 / Hour $15 / Hour
Y 100% $15 / Hour $20 / Hour
Z 100% $20 / Hour $25 / Hour
8. Create the WBS format and key in resource usage information, activities’ % completes and actual costs. Do NOT leveling resources (let resources working overtime).Answer the following questions
a) What is the % complete for the Installation Phase summary task?
b) What is the % complete for the total project summary task?
c) What is the remaining work for the project?
d) What is the remaining duration for the project?
e) What is the planned cost for “Activity 2.2 E”?
9. What are your values for the following?
a) Planned Value (PV) =
b) Earned Value (EV) =
c) Actual Cost (AC) =
10. Calculate the Schedule Performance Index and Estimated Time to Finish.
11. Calculate the Cost Performance Index and Estimated Cost to Finish.